๐Project Registered๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Fort Worth Convention Center Phase 2 - Existing Restroom Renovations
1201 Houston Street, Fort Worth, TX, 76102
Pre-Construction15%
๐Project Metrics
TDLR #TABS2026008490$11.2M
Project Value
8,200
Square Feet
$1.36K/sqft
Cost/SqFt
5 months
Duration
Registered:Dec 18, 2025
Start:Mar 1, 2026
Target:Aug 1, 2026
Remaining:225 days
๐
Project Registered
Project has been registered with TDLR and is in pre-construction phase
๐Scope of Work
Restroom renovation
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
December 18, 2025
Construction Start
March 1, 2026
Expected Completion
August 1, 2026
๐Related Projects
Property Owner
๐ค
City of Fort Worth
Contact: Cynthia Serrano
4 projects ยท $13.2M
1201 Houston Street, Fort Worth, Texas 76102
Design Firm
๐๏ธ
Bennett Partners Architecture Interiors Planning
640 Taylor Street Suite 2323, Fort Worth, Texas 76102