AW - Walnut Creek WWTP Expansion to 100 MGD - Overall SP A
πDevelopment Metrics
Infrastructure Project
This site plan is for infrastructure/utility work. Typical development metrics (units, building area) may not apply.
Approved and Released
Site plan approved and released. Ready for permit issuance.
πProject Description
Applicant proposes wastewater Treatment Plant expansion project, consists of 5 phases, Pkg A (flood wall & drainage), Pkg B (existing plant), Pkg C (proposed plant), Pkg D (wet weather), Pkg E (outfall to Colorado River) PuPr1 WWTP PC = KW
π Entitlement Timeline
ποΈZoning & Land Use Analysis
Existing Conditions
Proposed Development
Review Requirements
πNearby Site Plans
Development activity within ~800m
ποΈNearby TDLR Projects
Active construction in the area
Applicant / Developer
City Case Manager
Location & Jurisdiction
Property Records
πAll Site Plan Data
Click to expand
πAll Site Plan Data
Click to expandIdentifiers
Project Numbers
Key Dates
Address
Zoning & Land Use
Geographic
Review Status
Applicant
Owner
ABS 4 SUR 19 BURLESON J ACR 303.615
SP-2025-0148D; SP-2025-0284D; SP-2025-0238D
Applicant proposes wastewater Treatment Plant expansion project, consists of 5 phases, Pkg A (flood wall & drainage), Pkg B (existing plant), Pkg C (proposed plant), Pkg D (wet weather), Pkg E (outfall to Colorado River) PuPr1 WWTP PC = KW