๐ŸProject Closed๐Ÿ—๏ธ New Construction๐Ÿ’ต This project involves public funds, public land, or is a Federally funded roadway project.

METRO NORTH CORRIDOR SEGMENT 4B

1900 MAIN, Houston, TX 77002, Houston, TX, 77002
Completed100%

๐Ÿ“ŠProject Metrics

TDLR #EABPRJB4804367
$200K
Project Value
โ€”
Square Feet
โ€”
Cost/SqFt
3y 10mo
Duration
Registered:Nov 13, 2013
Start:Feb 1, 2010
Target:Nov 1, 2013
๐Ÿ

Project Closed

Project has been completed and closed

๐Ÿ“‹Scope of Work

Re-construct main st bridge to handle the LRT facility from Main Street bridge station to Rothwell St, including

Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.

๐Ÿ“…Compliance Timeline

Project Registered
November 13, 2013
Construction Start
February 1, 2010
Expected Completion
November 1, 2013