๐Review Complete๐ง Renovation/Alteration๐ต This project involves public funds, public land, or is a Federally funded roadway project.
Phase 11 Street Reconstruction
Bartlett Dr, Miller Dr and Tucker St, The Colony, TX 75056, The Colony, TX, 75056
Construction50%
๐Project Metrics
TDLR #TABS2022010966$219K
Project Value
27,510
Square Feet
$8/sqft
Cost/SqFt
1y 8mo
Duration
Registered:Feb 4, 2022
Start:Apr 1, 2022
Target:Nov 30, 2023
๐
Review Complete
Design review complete, construction may proceed
๐Scope of Work
Reconstruction of Bartlett Drive, Miller Drive, and Tucker Street including new pavement, sidewalk and ramps, alleys, drainage, and utilities.
Note: This project is registered under the Texas Accessibility Standards (TAS) program. TDLR registration is required for commercial and public facility construction to ensure compliance with accessibility requirements under Texas Government Code Chapter 469.
๐ Compliance Timeline
Project Registered
February 4, 2022
Construction Start
April 1, 2022
Expected Completion
November 30, 2023
๐Related Projects
๐คSame Owner
$10.0M totalProperty Owner
Design Firm
๐๏ธ
Halff Associates, Inc.
4 projects ยท $5.5M
4000 Fossil Creek Blvd., Fort Worth, Texas 76137