Austin, Texas — Nov. 24, 2026. The City of Austin issued a $2.3 million building permit on Nov. 20 to turn a metal warehouse at 504 Industrial Blvd. in St. Elmo into "indoor sports and recreation." A separate state filing names the project: Third Wave, a climbing gym. Third Wave's own website now says it opens in summer 2027, and a $5 refundable deposit is already open for pre-opening memberships. According to ATX Things' read of the public filings, the permit, the state registration and the gym's own pages agree on the big picture and disagree on the details.

Note

Sister-site disclosure. Austin Local Team (austin.localteam.house) is a sister site of Austin Texas Things, and this is our weekly piece pointing to it. Austin Local Team is brokered by All City Real Estate, ltd. Co. (TREC #9003633); its About page carries the TREC Information About Brokerage Services and Consumer Protection Notice. We have not been inside this building, and nothing here is a listing or real-estate advice.

What does the permit at 504 Industrial Blvd. actually say?

The City of Austin record is permit 2026-147575 BP, a commercial "Addition and Remodel." Here is what it states, as read from the city's public permit search on Nov. 24:

FieldWhat the record says
Address504 Industrial Blvd., Austin, TX 78745 (council district 3)
WorkChange of use of an existing metal warehouse building to indoor sports and recreation, including a new mezzanine, associated mechanical/electrical/plumbing work and fire protection
Valuation$2,300,000
Applied / issuedSept. 23, 2026 / Nov. 20, 2026
ContractorMiars Construction
New or added floor area3,779 sq ft (as shown on a mirror of the city record)

The permit never says "climbing." "Indoor sports and recreation" could be a soccer box or a trampoline park. What names the tenant is a second filing, and that one is easy to miss.

Pro Tip

A change-of-use permit like this one means the building's legal use is changing. It is not a certificate of occupancy and not an opening date. Inspections come after construction, and the permit status on the city site will say "Active" for months.

Which business is behind it?

The Texas Department of Licensing and Regulation (TDLR) keeps a public registry of commercial construction projects, filed for accessibility review. Project TABS2027000777 was registered Sept. 10, 2026 under the name "3rd Wave Climbing Gym," at the same address, with the same $2.3 million estimated cost.

The state filing is more specific than the city's:

  • Scope: renovation and change of occupancy of an existing warehouse into "an indoor climbing gym facility, including climbing areas, fitness areas, co-working space, accessory retail sales"
  • Size: 20,000 square feet
  • Dates: start Nov. 1, 2026, completion May 31, 2027
  • Money: privately funded, on private land, with the private funds provided by the tenant
  • Status on Nov. 24: "Review Complete"
  • Design firm: Shelton Architecture, LLC. Owner of record: Prospect Capital Holdings LLC, with an address on East St. Elmo Road

That last line matters for anyone who lives nearby: a building owner and a tenant are two different parties here, and the filing says the tenant is paying.

Metal warehouse building with a chain-link fence beside a live oak tree in South Austin at golden hour

AI-generated illustration of a typical St. Elmo-area warehouse, not a photograph of 504 Industrial Blvd.

What does Third Wave say it is building?

Third Wave's website (thirdwaveatx.com), read Nov. 24, says "Opening Summer 2027 in St. Elmo." The pages describe:

  • 7,000+ square feet of bouldering, with routes reset every four weeks
  • A full gym with cardio, an outdoor yard and a yoga/pilates studio
  • A sauna garden and three cold plunges
  • Coffee on the patio and co-working upstairs

A climber's chalked hands gripping a hold on an angled bouldering wall

AI-generated illustration of bouldering, not a photo of Third Wave.

The pre-opening membership is a $5 deposit that holds a spot, with the first month free and no initiation fee, per the gym's membership page. The fine print says the deposit is refundable by emailing the gym, and that if the opening date moves, members can stay in or take a full refund. We did not test that process. We do not know the monthly price, the day-pass price or the hours, because the site does not list them yet.

Why do the numbers not match?

They are measuring different things, and they have also moved over time. Put side by side:

SourceDateWhat it says
Congress Lofts at St. Elmo (Instagram, welcoming the gym)Nov. 4, 2025"Opening 2026"; 10,000+ sq ft of bouldering surface; about 150 dedicated parking spaces
Austin Business Journal (Sept. 22, 2026 story; post on X)Sept. 2026Converting a 25,000-square-foot warehouse
TDLR filingSept. 10, 202620,000 sq ft facility; completion May 31, 2027
City permitNov. 20, 2026$2.3M; 3,779 sq ft new or added floor area
thirdwaveatx.comNov. 24, 20267,000+ sq ft of bouldering; opening summer 2027

Three things follow. The "opening 2026" line from a year ago did not hold; the gym now says summer 2027, and the state filing's May 31, 2027 completion date fits that. "Bouldering surface" is the climbable wall area, which is a different measure than the building's footprint, so 7,000 and 10,000 are not necessarily a contradiction. And the 150 parking spaces came from a neighboring building's post, not from the gym or the city, so treat it as unconfirmed until Third Wave publishes a site plan.

Heads Up

Nothing in these records gives an opening day. The state's completion date is a construction target, and the gym's "summer 2027" is the only public opening estimate we found. Dates on projects like this slide.

How can you check a permit like this near your own address?

This is the part worth keeping. Any address in Austin has a paper trail you can read in about ten minutes, for free:

  1. City permits. Search the address on the City of Austin's permit portal. Look at the description, the issue date and the status, not just the dollar figure.
  2. TDLR project registrations. Commercial and public projects over a cost threshold are registered at tdlr.texas.gov/TABS. The scope text and the tenant/owner fields often name the business before any press release does.
  3. Site plans. Larger projects file a site plan with the city. A site plan is a proposal, not an approval.
  4. Cross-check the business's own pages. Compare what it says with what it filed. When they differ, say so rather than picking one.

Our ZIP 78745 page pulls the same filings together for the postal ZIP, and the 800-meter check walks through doing it around a specific home.

What else has been filed in 78745?

For context, Austin Local Team's 78745 page (rollup generated Nov. 24, 2026, Austin permit sync Nov. 22 and TDLR sync Nov. 24) counts 39 TDLR project registrations and 13 site-plan applications in the ZIP over the past 12 months. Those are filings, not a description of any block or resident, and a postal ZIP is not a neighborhood boundary. The 504 Industrial Blvd. registration (Sept. 10) falls inside that window.

If you live or are looking near St. Elmo and want the same records laid around a specific address, Austin Local Team's 78745 ZIP guide lists permits, site plans and TDLR registrations as counts, with the source and sync date on each. It does not rate any area, and we do not either. It is a sister site of ours, as noted above.

What should locals know before the doors open?

  • Nothing is open. The building is a permitted construction site as of this week. We have not visited, and no one should show up expecting to climb.
  • The $5 deposit is real but optional. It is on the gym's own page, with a stated refund path. Decide with the fine print in front of you.
  • Watch the permit. Status changes, inspection entries and any new filings at this address will show up on the city portal before an opening announcement does.
  • Nearby context: St. Elmo already has Pins Mechanical Co., a duckpin bowling and social space we covered in December 2025.

FAQ

Is Third Wave Climbing Gym open yet? No. Third Wave's website says it opens in summer 2027. The City of Austin issued the building permit on Nov. 20, 2026, and the state filing lists a May 31, 2027 completion date.

Where is Third Wave in Austin? 504 Industrial Blvd., Austin, TX 78745, per the city permit and the TDLR filing. The gym's Instagram profile places it in the St. Elmo Arts District.

How much is the project worth? $2.3 million, per both the city permit and the state registration. The state filing says it is privately funded.

How big is it? It depends on what you measure. The state filing says 20,000 square feet. The gym's website says 7,000+ square feet of bouldering. The city permit lists 3,779 square feet of new or added floor area.

Can I sign up now? The gym's membership page offers a $5 deposit for a pre-opening membership with the first month free, refundable per its fine print.

Sources: City of Austin permit 2026-147575 BP (issued Nov. 20, 2026); TDLR TABS project TABS2027000777 (registered Sept. 10, 2026); thirdwaveatx.com (read Nov. 24, 2026); Congress Lofts at St. Elmo on Instagram (Nov. 4, 2025); Austin Business Journal (Sept. 22, 2026); Austin Local Team ZIP 78745 page (Nov. 24, 2026). Development records tracked by ATX Things.